Get instant access to C_IBP_2105 Practice Tests 2021 Free Updated Today!
Welcome to download the newest PassLeader C_IBP_2105 PDF dumps ( 82 Q&As)
NEW QUESTION 13
You need to create time periods for the time profile in a planning are
a. What should you be aware of when executing the Create Time Periods application job?
- A. A time profile has to be activated so that the application job can proceed.
- B. This application job cannot be scheduled for immediate start.
- C. The planning area with this time profile must be activated so that the application job can proceed.
- D. This application job can be run for multiple time profiles at once.
Answer: C
NEW QUESTION 14
You have set up infinite S&OP heuristics for unconstrained planning. What must you do to model inputs as constraints? Note: There are 2 correct Answers to this question.
- A. Set minimum and maximum lot sizes.
- B. Model adjusted transport receipts.
- C. Create product substitutions.
- D. Enter transportation lead times.
Answer: B,D
NEW QUESTION 15
You are modeling the introduction of a new product using Lifecycle Planning functionality in SAP IBP.
What is mandatory to create in your planning area for the setup of reference product(s) to work? Note:
There are 2 correct Answers to this question.
- A. Definition of an attribute representing the product description
- B. Definition of an attribute representing the product ID
- C. Definition of Actual Sales business meaning for one key figure
- D. Planning objects for the new product
Answer: B,D
NEW QUESTION 16
A time profile is defined with the levels of day, technical week, week, month, quarter, and year. What condition in configuration will allow you to have a different value in the current week, versus all other buckets?
- A. IF("PERIODID5" ="$$PERIODID5CU$$...)
- B. IF("PERIODID4" ="$$PERIODID4CU$$...)
- C. IF("PERIODID2" ="$$PERIODID2CU$$...)
- D. IF("PERIODID3" ="$$PERIODID3CU$$...)
Answer: B
NEW QUESTION 17
Which of the following modes can you use when creating a constrained plan? Note: There are 2 correct Answers to this question.
- A. Delivery maximization
- B. Production maximization
- C. Profit maximization
- D. Resource maximization
Answer: A,C
NEW QUESTION 18
Which of the following key functions are supported by SAP IBP for sales and operations? Note: There are
2 correct Answers to this question.
- A. An advanced demand planning process
- B. A basic demand planning process
- C. Finite resource planning
- D. Manual creation of feasible constrained plans
Answer: B,C
NEW QUESTION 19
You are working to realign the data due to a recent warehouse closure. What should you be aware of in regards to configuration of realignment steps? Note: There are 2 correct Answers to this question.
- A. The number of steps in realignment run is limited to 255.
- B. If a realignment step fails, subsequent steps are not processed.
- C. The name of the realignment step should be no longer than 20 characters.
- D. The realignment step status must be set to Approved for it to be executed.
Answer: B,D
NEW QUESTION 20
Which one of the following values can you use in disaggregation expressions?
- A. KF1 (Calculated) + Attribute
- B. KF1 (Stored) + Helper KF
- C. If (Attribute)=0
- D. KF1 (Stored) + KF2 (Stored) + Attribute
Answer: C
NEW QUESTION 21
While modeling costs for optimization, you are conscious of the necessity to respect inventory targets and meet demands in the short term. Which of the following are valid relationships between costs you must adhere to? Note: There are 2 correct Answers to this question.
- A. Target inventory violation cost should be greater than inventory holding cost rate.
- B. Target inventory violation cost should be greater than discount for demand lateness.
- C. Target inventory violation cost should be less than transportation cost rate.
- D. Target inventory violation cost should be less than max inventory violation cost.
Answer: A,C
NEW QUESTION 22
You want to restrict value entries outside of a specified range into a key figure. What setting will you use to achieve that goal?
- A. IBP -> Lock Selected cells in IBP Formatting Sheet tab
- B. IBP -> Data Validation in IBP Formatting Sheet tab
- C. Select Protect Active Worksheet in the About section of SAP IBP tab
- D. By restricting data input in the Key Figure Configuration app
Answer: D
NEW QUESTION 23
You are reviewing the master data types for supply planning. Which master data types are compound master data types? Note: There are 2 correct Answers to this question.
- A. SOURCECUSTOMER
- B. SOURCEPRODUCTION
- C. LOCATIONFR
- D. SOURCELOCATION
Answer: A,D
NEW QUESTION 24
You run a what-if analysis and use the scenario planning function. Which actions can you perform? Note:
There are 3 correct Answers to this question.
- A. Run a scenario-specific inventory optimization job.
- B. Run a scenario-specific demand sensing job.
- C. Display data in analytics.
- D. Change scenario-specific master data.
- E. Share data with other users.
Answer: A,C,E
NEW QUESTION 25
What function would you use to configure a year-to-date calculation?
- A. Dynamic Rolling Aggregation
- B. Last Period Aggregation
- C. Cumulative Aggregation
- D. Rolling Aggregation
Answer: C
NEW QUESTION 26
You are adding a value-based filter to a planning view. Which of the following conditions apply? Note:
There are 3 correct Answers to this question.
- A. These filters are always applied based on the values stored in the database.
- B. You can only apply one value-based filter per planning view.
- C. The alerts dashboard is not available if a value-based filter is set for the open planning view.
- D. These filters can be used together with attribute totals in the same planning view.
- E. You can add (or delete) planning objects to a planning view after these filters are applied.
Answer: A,B,C
NEW QUESTION 27
Which calculations can be processed within the pre-processing step in the forecasting model? Note:
There are 2 correct Answers to this question.
- A. Rounding can be executed for the sales history.
- B. Correlations can be evaluated.
- C. Promotion Sales Lift Ups can be deleted.
- D. Missing Values can be substituted.
Answer: C,D
NEW QUESTION 28
Which of the following solutions are feasible when using the time series supply optimizer? Note: There are 3 correct Answers to this question.
- A. Violation of minimum resource utilization
- B. Violation of minimum aggregated inventory values
- C. Not respecting production capacity
- D. Not adhering to maximum transport values
- E. Not-fully satisfied demands
Answer: A,B,E
NEW QUESTION 29
......
Sep-2021 Latest TestSimulate C_IBP_2105 Exam Dumps with PDF and Exam Engine: https://www.testsimulate.com/C_IBP_2105-study-materials.html