The individuals who achieve the passing score in the Cisco 300-630 exam fulfill part of the requirements for getting the CCNP Data Center certification (they have to nail the 350-601 DCCOR test as well). With this certificate, the specialists can explore a wide range of job roles, such as a Data Center Engineer, a Senior Network Engineer, a Data Center Technician, a Technical Consulting Engineer, a Data Center Support, and a Network Analyst. The average salary outlook for the certified professionals is $79,000 per annum. Some senior-level applicants can earn $111,000 per year.
NEW QUESTION 21
What is a design implication for Cisco ACI using an application-centric approach?
- A. VLAN numbers are in the names of the bridge domain and EPG objects
- B. One EPG is mapped to multiple bridge domains
- C. One VLAN equals one EPG equals one bridge domain
- D. Multiple VLANs and/or multiple EPGs are under one bridge domain
Answer: B
NEW QUESTION 22
An engineer deploys a Cisco ACI Multi-Site Orchestrator for the first time. Drag and drop the actions from the left into the steps on the right to add a site and deploy new Cisco ACI objects to the fabric. Not all actions are used.
Answer:
Explanation:
NEW QUESTION 23
An engineer designs a Cisco ACI Multi-Pod solution that requires a pair of active-standby firewalls in different pods for external connectivity. How should the firewalls be implemented?
- A. routed firewall for the default gateway
- B. transparent firewalls
- C. separate L3Out peerings for routed firewalls
- D. PBR for routed firewalls
Answer: B
Explanation:
Section: Multipod
Explanation/Reference: https://www.cisco.com/c/en/us/solutions/collateral/data-center-virtualization/application-centric- infrastructure/white-paper-c11-739571.html
NEW QUESTION 24 

Refer to the exhibits. Which subject must be configured for the All_noSSH contract to allow all IP traffic except SSH between the two EPGs?
- A.

- B.

- C.

- D.

Answer: B
Explanation:
Section: Advanced ACI Policies and Integrations
Explanation/Reference: https://www.cisco.com/c/en/us/td/docs/switches/datacenter/aci/apic/sw/1-x/ACI_Best_Practices/ b_ACI_Best_Practices/b_ACI_Best_Practices_chapter_010.html
NEW QUESTION 25
How does Cisco ACI manage the STP BPDUs between two pods?
- A. Cisco ACI spines suppress STP BPDUs to be forwarded to other pods
- B. Cisco ACI spines perform ingress replication for STP BPDUs
- C. Special multicast group 239.255.255.255 is used to forward STP BPDUs
- D. BPDUs are forwarded over IPN using the bridge domain GIPo multicast address
Answer: D
NEW QUESTION 26
Which two actions should be taken to ensure a scalable solution when multiple EPGs in a VRF require unrestricted communication? (Choose two.)
- A. Set the EPGs that require policy enforcement between each other as preferred group members.
- B. Set the EPGs that require unrestricted communication between each other as preferred group members.
- C. Configure a taboo contract between the EPGs that require unrestricted communication between each other.
- D. Enable Preferred Group Member under the EPG Collection for VRF section.
- E. Set the VRF policy control enforcement preference to Unenforced.
Answer: B,E
Explanation:
Section: Advanced ACI Policies and Integrations
Explanation/Reference: https://www.cisco.com/c/en/us/td/docs/switches/datacenter/aci/apic/sw/4-x/basic-configuration/ Cisco-APIC-Basic-Configuration-Guide-42x/Cisco-APIC-Basic-Configuration-Guide-42x_chapter_0110.html
NEW QUESTION 27
Refer to the exhibit.
Which combination of flags in the Cisco ACI contract allows a client in WebClient EPG to establish an HTTP connection toward a server in WebServer EPG?
- A. Apply Both Direction ENABLED and Reverse Port Filter ENABLED
- B. Apply Both Direction ENABLED and Reverse Port Filter DISABLED
- C. Apply Both Direction DISABLED and Reverse Port Filter DISABLED
- D. Apply Both Direction DISABLED and Reverse Port Filter ENABLED
Answer: D
NEW QUESTION 28
An engineer creates the objects that must be deployed at each site in Cisco ACI Multi-Site Orchestrator. Which action should be taken before the schema can be associated with the newly configured site?
- A. Configure a provider for the Cisco ACI Multi-Site Orchestrator
- B. Import existing policies from an existing tenant to Cisco ACI Multi-Site Orchestrator
- C. Configure the Infra Site-Specific Settings
- D. Attach the templates to the newly configured site
Answer: D
Explanation:
Section: Multisite
NEW QUESTION 29
Drag and drop the tenant implementation designs from the left onto the outcomes of the design when a greenfield Cisco ACI fabric is deployed on the right.
Answer:
Explanation:
NEW QUESTION 30
Which approach does Cisco ACI use to achieve multidestination packet forwarding between leaf switches in the same fabric?
- A. Map VXLAN VNI to the multicast group
- B. Map VXLAN to PIM-SM protocol
- C. Map VXLAN to PIM-DM protocol
- D. Map VXLAN VTEP to the multicast group
Answer: A
NEW QUESTION 31
Which two actions should be taken to ensure a scalable solution when multiple EPGs in a VRF require unrestricted communication? (Choose two.)
- A. Set the EPGs that require policy enforcement between each other as preferred group members.
- B. Set the EPGs that require unrestricted communication between each other as preferred group members.
- C. Configure a taboo contract between the EPGs that require unrestricted communication between each other.
- D. Enable Preferred Group Member under the EPG Collection for VRF section.
- E. Set the VRF policy control enforcement preference to Unenforced.
Answer: B,E
NEW QUESTION 32
Refer to the exhibit.
What must be configured to allow the PBR node (LB-int) to monitor the availability of the endpoint that is in the EPG server?
- A. Direct Connect in the service graph template
- B. Unicast Route disabled for client and server bridge domains
- C. PBR node tracking
- D. Endpoint Dataplane Learning
Answer: D
NEW QUESTION 33
What is the advantage of implementing an active-active firewall cluster that is stretched across separate pods when anycast services are configured?
- A. A cluster can be deployed in transparent mode across pods.
- B. Local traffic in a pod is load-balanced between the clustered firewalls.
- C. The local pod anycast node is preferred by the local spines.
- D. A different MAC/IP combination can be configured for the firewall in each pod.
Answer: D
NEW QUESTION 34
What are two characteristics of network-centric design in Cisco ACI? (Choose two.)
- A. EPGs are different security zones
- B. A bridge domain has one subnet and one EPG
- C. There is open communication between EPGs
- D. EPGs are used for microsegmentation
- E. Applications define the network requirements
Answer: B,D
NEW QUESTION 35
An engineer implements the Cisco ACI solution and needs to confirm that the leaf switch correctly learns the remote endpoint MAC. Which information must be included in the VXLAN packet that is received from the Cisco ACI spine for the Cisco ACI leaf to learn MAC as a remote endpoint?
- A. EPG
- B. VRF
- C. bridge domain
- D. application profile
Answer: C
Explanation:
Reference:
https://www.cisco.com/c/en/us/solutions/collateral/data-center-virtualization/application-centric-infrastructure/ white-paper-c11-739989.html
NEW QUESTION 36
An engineer configures a new Cisco ACI Multi-Pod and must set up the link between the spine and the IPN device. Which three actions should be taken to accomplish this goal? (Choose three.)
- A. Enable BIDIR-PIM protocol
- B. Enable OSPF routing
- C. Enable DHCP relay
- D. Enable IS-IS routing
- E. Enable PIM-SM protocol
- F. Enable MP-BGP routing
Answer: A,C,F
Explanation:
Section: Multipod
NEW QUESTION 37
Refer to the exhibit.
A customer experiences resource overconsumption on one of its border leaf switches. Which action should be taken to reduce the consumption on this switch?
- A. Disable IP Data Plane Learning
- B. Migrate L3Outs to another switch
- C. Disable Remote EP Learning
- D. Disable VRF Policy Control Enforcement
Answer: A
NEW QUESTION 38
Refer to the exhibit.
How is the ARP request from VM1 forwarded when VM2 is not learned in the Cisco ACI fabric?
- A. Leaf 101 encapsulates the ARP request into a multicast packet that is destined to 225.0.37.192.
- B. Leaf 101 forwards the ARP request to one of the proxy VTEP spines.
- C. POD1 spine responds to the ARP request after the POD1 COOP is updated with the VM2 location.
- D. Leaf 101 switch consumes the ARP reply of VM2 to update the local endpoint table.
Answer: B
NEW QUESTION 39
Which firewall connection allows for the integration of service nodes in transparent mode with a Cisco ACI Multi-Pod setup?
- A. active-standby mode per pods for communication between endpoints and external networks
- B. active-active mode per pods for communication between internal endpoints
- C. active-standby mode across pods
- D. active-active mode across pods
Answer: C
NEW QUESTION 40
......
What Happens After Clearing Implementing Cisco Application Centric Infrastructure â Advanced (300 - 630) Exam
- The Cisco Certification Tracking System records exam and certification status. Keep your contact information up to date to receive notifications about your certification.
- After youâre certified, you will be authorized to use the Cisco Certification logo that identifies your status. Before using a logo, you must read and acknowledge the Cisco Certifications Logo Agreement. You can download logos through the Certifications Tracking System.
- Every written proctored exam passed equals a Specialist certification
- Within 24 hours of passing your certifying exam you will receive an email advising you on the next steps. You must complete the steps to trigger the fulfillment process.
How to Prepare for CISCO 300-630 Implementation of Application Centric Infrastructure Advanced (DCACIA)
Preparation Guide for CISCO 300-630 Implementation of Application Centric Infrastructure Advanced (DCACIA)
Introduction for CISCO 300-630 Implementation of Application Centric Infrastructure Advanced (DCACIA)
The CISCO 300-630 Implementation of Application Centric Infrastructure Advanced (DCACIA) test reveals to you the most ideal approach to facilitate the limits of the Cisco Nexus 9000 Series Switches in Cisco Application Centric Infrastructure (Cisco Application Centric Infrastructure) mode. You will sort out some way to plan and administer Cisco Nexus 9000 Series Switches in ACI mode giving overhauled the chiefs and methodology framework, close by the shows used in the fundamental surface. The test moreover covers how to use Cisco Application Centric Infrastructure as a plan driven course of action that fuses programming and gear, and directions to execute Cisco Application Centric Infrastructure Multi-Pod and Multi-Site plans. You will secure included work on completing front line ACI limits, for instance, Rogue CISCO Endpoint Feature, Transit Routing, Configure & Test VRF Route Leaking, Assesing Contracts and Multi-Zoning Rules. This also includes Policy Based Redirect to Multi-Pod Fabric and ACI Orchestrator.
Cisco 300-630 Application Centric Infrastructure (DCACIA 300-630) is an approx 90 minutes test related with the Cisco Certified Specialist â ACI Advanced Implementation authentication. Thistest a candidate’s general data and capacities of Cisco switches in ACI mode including course of action, execution, the board, and exploring.
With this test you will really need to:
- Learn best practices for executing and managing Cisco Nexus 9000 Series Switches in Cisco Application Centric Infrastructure mode
- Leverage the coordination programming and gear answers for develop the limits of worker ranch and cloud associations
- Maximize the upsides of an application-driven approach to manage pass on robotization and versatility in IT benefits, and automate surface association and arrangement
To totally benefit by this test, you should have the going with data and capacities:
- Familiarity with virtualization fundamentals
- Understanding of Cisco worker ranch designing
- Basic understanding of Cisco Application Centric Infrastructure
Ensuing to stepping through this exam, you should have the alternative to:
- Configure Cisco Application Centric Infrastructure Service Graph Policy-Based Redirect (PBR)
- Understand the nuances and considered completing and planning regular association with Cisco Application Centric Infrastructure
- Demonstrate Cisco Application Centric Infrastructure Multi-Pod plan
- Integrate Cisco Application Centric Infrastructure advanced surface pack sending
- Implement advanced ACI procedure and occupant arrangement
- Describe Cisco Application Centric Infrastructure Multi-Site plan
We offer CISCO 300-630 practice exam and CISCO 300-630 practice tests for the best insight.
Download Real Cisco 300-630 Exam Dumps Test Engine Exam Questions: https://www.testsimulate.com/300-630-study-materials.html