NEW QUESTION # 28
For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.
- A. The consistency check must be performed.
- B. The deletion flag must NOT be set for the bill of material (BOM) or the routing.
- C. The assigned routing and bill of material (BOM) must be valid in the entire validity period.
- D. The lot size range must be within the lot size range of the assigned routing.
- E. The assigned routing and bill of material (BOM) must have the same validity period.
Answer: A,C,D
NEW QUESTION # 29
What are some options for creating production orders without using trigger points?
Note: There are 2 correct answers to this question.
- A. In assembly production, a sales order triggers the creation of a production order
- B. In make-to-stock production, you can manually create production orders
- C. In make-to-stock production, confirmation of yield for sub-assembly triggers the creation of a production order
- D. In assembly production, confirmation of scrap triggers the creation of a production order
Answer: A,B
NEW QUESTION # 30
How can you set up a material as a phantom assembly?
Note: There are 2 correct answers to this question.
- A. Select a special procurement type inside the material BOM (bill of material)
- B. Select a special explosion type inside the material BOM (bill of material)
- C. Select a special procurement type inside the material master
- D. Select a special explosion type inside the material master
Answer: A,C
NEW QUESTION # 31
What is the purpose of the pull list in material staging?
- A. To control the flow of material from the central storage location to the production storage location
- B. To control the flow of material from the supplier to the production storage location
- C. To control the flow of material from the supplier to the central storage location
- D. To control the flow of material from the production storage location to the central storage location
Answer: A
NEW QUESTION # 32
Which alternative item strategies are available in bills of material (BOMs)?
Note: There are 2 correct answers to this question.
- A. Manual maintenance
- B. 100% check
- C. Simultaneous
- D. Ranking
Answer: A,B
NEW QUESTION # 33
Which of the following are features of the clean core dashboard?
Note: There are 2 correct answers to this question.
- A. Customers can use the dashboard in the dev, test, and production tenants.
- B. It can be used in all SAP S/4HANA Cloud editions.
- C. It can be accessed by using SAP For Me.
- D. Customers can grant access to the dashboard to partners.
Answer: C,D
NEW QUESTION # 34
Which of the following are scheduling time elements for a production order?
Note: There are 3 correct answers to this question.
- A. Setup time
- B. Queue time
- C. Float before production
- D. Transit time
- E. Load time
Answer: A,B,C
NEW QUESTION # 35
What are some SAP recommended guiding principles to achieve clean core operations?
Note: There are 3 correct answers to this question.
- A. Establish release management.
- B. Establish an organizational structure, technical foundation, and transformation methodology for clean core.
- C. Establish regular housekeeping tasks and procedures.
- D. Define roles and responsibilities as part of a process transformation office.
- E. Integrate clean core practices in the end-to-end value process chain.
Answer: A,B,D
NEW QUESTION # 36
What does forecasting in the demand planning cycle include?
Note: There are 3 correct answers to this question.
- A. Past quotation quantities
- B. Past production planning quantities
- C. Market intelligence
- D. Past sales order quantities
- E. One-off events
Answer: C,D,E
NEW QUESTION # 37
Which planning strategies can you use in the capacity scheduling table?
Note: There are 2 correct answers to this question.
- A. Planning mode > Order priority
- B. Scheduling control > Find slot
- C. Scheduling control > Close gap
- D. Planning mode > Bucket
Answer: B,D
NEW QUESTION # 38
How do you model a production line in repetitive manufacturing?
- A. As a routing
- B. As a work center
- C. As a resource network
- D. As an operation
Answer: B
NEW QUESTION # 39
How can you achieve a feasible production plan when there are capacity constraints?
Note: There are 3 correct answers to this question.
- A. Reduce the planning time interval
- B. Increase the capacity supply in a time-phased interval
- C. Form optimum sequences to reduce setup times
- D. Determine a time period with available capacity on the planning board
- E. Execute an infinite production planning run for the critical resources
Answer: B,C,D
NEW QUESTION # 40
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. When does the BOM need to become effective?
- B. In which storage location is the BOM required?
- C. Which base unit of measure must the BOM have?
- D. For which plant can the BOM be defined?
Answer: A,D
NEW QUESTION # 41
Which order type is used for repetitive manufacturing?
- A. Production order
- B. Planned order
- C. Process order
- D. Kanban order
Answer: B
NEW QUESTION # 42
How would you define a pegging structure for an order in the context of Advanced Planning?
- A. An evaluation that is ordered according to the low-level codes of all related products and represents the coverage of issue elements with receipt elements and stock
- B. An evaluation to identify overstock situations based on the assignment of receipt and issue elements after the production planning run
- C. An evaluation to identify material or capacity shortages in the bill-of-material structure after the production planning run
- D. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between receipt and issue elements
Answer: D
NEW QUESTION # 43
You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received.
Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semi-finished material?
- A. Planning with final assembly (40)
- B. Assembly processing with production orders (82)
- C. Planning at assembly level (70)
- D. Production by lot size (30)
Answer: C
NEW QUESTION # 44
Which time elements are relevant for lead time scheduling of a production order?
Note: There are 2 correct answers to this question.
- A. Setup time
- B. Float after production
- C. Opening period
- D. Total replenishment lead time
Answer: A,B
NEW QUESTION # 45
Which operations are considered in the capacity scheduling table?
Note: There are 2 correct answers to this question.
- A. Operations assigned to a pacemaker work center
- B. Only bottleneck operations
- C. Sub-operations
- D. All operations
Answer: B,C
NEW QUESTION # 46
Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question.
- A. Operation duration
- B. In-house production time
- C. Planned delivery time
- D. Total replenishment lead time
Answer: B,C
NEW QUESTION # 47
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. Order (pool) chart
- B. Capacity requirements chart
- C. Order (dispatched) chart
- D. Work center capacities chart
Answer: B,D
NEW QUESTION # 48
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.
- A. Scheduling agreement schedule line
- B. Purchase order
- C. Production order
- D. Planned order
Answer: A,D
NEW QUESTION # 49
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?
- A. To create a slot, neighbouring operations are moved in both planning directions.
- B. Operations on multi-resources are planned finitely in a sequence.
- C. An operation is scheduled as close as possible to the desired date.
- D. Sequencing on multi-activity resources is automatically updated during planning.
Answer: C
NEW QUESTION # 50
......