NEW QUESTION 81
True or False: The Sprint length can be thought of as the team's batch size with Scrum Teams using Kanban.
- A. Choose only ONE best answer.
- B. TRUE
- C. FALSE
Answer: C
NEW QUESTION 82
Which of the following best describes Kanban? (choose the best answer)
- A. A strategy for optimizing the flow of value through a process that uses a visual, Work in Progress (WIP) limited pull system.
- B. A process of defining a Scrum Team's workflow in order to increase productivity.
- C. None of the above.
- D. Additional practices that are integrated into the Scrum framework.
Answer: A
NEW QUESTION 83
True or False: Batch size is the same as the Sprint length when using Scrum with Kanban.
- A. False
- B. True
Answer: A
NEW QUESTION 84
Which of the following helps Scrum Teams, that use Kanban, from exceeding their capacity limits? (choose the best answer)
- A. Explicit Work In Progress (WIP) Limit policies.
- B. Having daily meetings about work in progress.
- C. Setting a robust Kanban workflow.
- D. Managing individual workloads of team members.
Answer: A
NEW QUESTION 85
Which of these are LEAST likely to be included in the definition of "Workflow" policies? (choose the best three answers)
- A. Definition of Done.
- B. Service Level Expectations.
- C. Work Item types.
- D. A Gantt chart.
- E. A Burndown chart.
- F. Visualization policies.
- G. WIP Limits.
- H. Pull/prioritization policies.
- I. The Increment.
Answer: D,E,I
NEW QUESTION 86
Work Item Age is best described as: (choose the best answer)
- A. The amount of elapsed time between when a work item entered the Product Backlog and the current time.
- B. The amount of elapsed time between when a work item entered the Sprint Backlog and the current time.
- C. The amount of elapsed time between when a work item "started" and the current time.
- D. The amount of elapsed time between the start of the Sprint and the current time.
Answer: C
NEW QUESTION 87
True or False: A team should change their WIP limit, at the Daily Scrum, if an urgent unplanned item enters a Sprint and the team is at the maximum WIP limit.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 88
True or False: The Sprint Retrospective is the only time in which the Work in Progress (WIP) Limit can change.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 89
The goal of the WIP Limit is to:
- A. allow the team to release multiple times per Sprint.
- B. increase the utilization rate of the Developers.
- C. make it easier for the Scrum Master to manage the tasks.
- D. maximize the amount of actual work in process.
- E. reduce the amount of actual work in process.
Answer: E
NEW QUESTION 90
What can a specific work item's Cycle Time metric be used for? (choose the best three answers)
- A. To influence the team's Service Level Expectation (SLE).
- B. As a lagging indicator to the length of feedback loop for that Work Item.
- C. As a leading indicator to the length of feedback loop for that Work Item.
- D. To help the team inspect and adapt their process.
- E. To help the team inspect and adapt their Sprint in the Daily Scrum.
Answer: A,B,D
NEW QUESTION 91
True or False: Explicit policies applied at each state/column of the workflow can replace the need for a definition of "Done".
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 92
True or False: The primary purpose of measuring Work Item Age is to identify bottlenecks in the workflow that will need to be addressed.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 93
Which of these metrics is most valuable for Sprint Planning? (Choose the best answer)
- A. Throughput.
- B. Cycle time.
- C. Points Delivered.
- D. Work Item Age.
Answer: A
NEW QUESTION 94
What might be discussed during the Sprint Retrospective if the Scrum Team is considering to use Kanban to complement their Scrum? (choose the best answer)
- A. Work in Progress (WIP) Limits.
- B. Current policies.
- C. Metrics and charts such as cumulative flow, scatterplot, and work item aging.
- D. All of the above.
- E. Workflows.
Answer: D
NEW QUESTION 95
True or False: Components of the Scrum framework needs to be adapted when Scrum Teams start using Kanban. Choose only ONE best answer.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 96
Which analytics chart will help to determine when a specific Product Backlog item, that is currently 'in progress', is projected to be 'finished'? (choose the best answer)
- A. Gantt chart.
- B. Work Item Aging chart.
- C. Throughput chart.
- D. Cumulative Flow Diagram (CFD) chart.
- E. Control chart.
Answer: B
NEW QUESTION 97
True or False: Professional Scrum with Kanban can be used without Work in Progress (WIP) Limits. (choose the best answer)
- A. False. WIP Limits are crucial to conducting Daily Stand Up meetings that control not having too much work.
- B. True. A strong team identity using Squads and tribes can be a valid alternative to WIP Limits.
- C. True. Physical Kanban boards can be used as an alternative to WIP Limits as it will improve visualization and enhance communication.
- D. False. Professional Scrum with Kanban cannot be used without explicit WIP Limits.
Answer: D
NEW QUESTION 98
Reducing batch sizes might have the following impact: (choose all that apply)
- A. Improving efficiency due to faster feedback loops.
- B. Higher motivation due to seeing your work get done and deliver value earlier.
- C. Highlight a need to improve processes/infrastructure to reduce the pain of frequent costly overhead.
- D. Lower efficiency due to overhead/transaction costs in case the batch size is too small.
Answer: A,B,C,D
NEW QUESTION 99
Who is accountable for managing the Kanban board in the Sprint Backlog? (Choose the best answer)
- A. The Scrum Master
- B. The Scrum Team
- C. The Product Owner
- D. The Developers
Answer: D
NEW QUESTION 100
A team is using Kanban to improve the Sprint flow by visualizing and managing flow in the Sprint Backlog.
Which of the following would be most helpful to visualize?
- A. Flow of tasks.
- B. Flow of invested effort.
- C. Flow of Product Backlog items.
- D. Flow of Story Points.
- E. Flow of only User Stories.
Answer: C
NEW QUESTION 101
True or False: Scrum events can be further enhanced by applying flow-based practices.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 102
Which is the most appropriate metric to look at if you want to determine when an item that that has NOT started might be finished?
- A. There is no such metric.
- B. Team Capacity.
- C. Historical Cycle Times.
- D. Team Velocity.
- E. Work Item Age.
Answer: C
NEW QUESTION 103
How does setting limits to Work in Progress (WIP) policies support self-management? (choose the best two answers)
- A. WIP Limits creates a boundary for which the Scrum Team self-manages within.
- B. As part of self-management Scrum Teams figure out their own WIP Limits.
- C. WIP Limits inhibit self-management since they limit the team's autonomy to pull work.
- D. A Scrum Master defines a WIP Limit to help the Scrum Team self-manage.
Answer: A,B