NEW QUESTION 44
You schedule a time-based single cycle plan with the following assigned planning data: Start date for Scheduling: 01.07.2023. Scheduling indicator: Time. Call Horizon: 20%. Cycle Modification Factor: 2.
Cycle/Unit: 10 DAY. What is the resulting call date?
- A. 21.07.2023
- B. 05.07.2023
- C. 27.06.2023
- D. 17.07.2023
Answer: B
NEW QUESTION 45
What is the purpose of configuring a structure indicator? Which of the following objects can you maintain when defining a structure indicator? Note: There are 2 correct answers to this question.
- A. Category of functional location
- B. Hierarchy levels
- C. Edit mask
- D. Equipment category
Answer: B,C
NEW QUESTION 46
You want to customize the business role for the maintenance technician. How do you proceed?
- A. You MUST assign a user status profile to the newly defined business role.
- B. You customize the SAP standard business role for the maintenance technician directly.
- C. You CANNOT customize business roles in the SAP S/4HANA Cloud system.
- D. You use the Create From Template option in the Maintain Business Roles application.
Answer: B
NEW QUESTION 47
You are in the screening phase of a Proactive Maintenance (4HI) process. What is the correct sequence of the next three process steps?
- A. Planning. Execution. Closure
- B. Planning. Approval. Closure
- C. Planning. Approval. Preparation
- D. Preparation. Approval. Execution
Answer: C
NEW QUESTION 48
Which SAP Fiori Apps allow you to check costs for preventive maintenance orders? Note: There are 2 correct answers to this question.
- A. Display Maintenance Plan
- B. Maintenance Plan Costing
- C. Manage Orders and Notifications in Information Center
- D. Display Maintenance Item
Answer: B,C
NEW QUESTION 49
What are key activities of the Prepare phase of the SAP Activate methodology? Note: There are 3 correct answers to this question.
- A. Project setup
- B. Starter system provisioning
- C. User training
- D. Customer self-enablement
- E. Data migration
Answer: A,B,D
NEW QUESTION 50
In what phase of the SAP Activate methodology do you test the business processes?
- A. Prepare
- B. Explore
- C. Deploy
- D. Realize
Answer: D
NEW QUESTION 51
In an emergency maintenance process, you want to control business transactions using a user status. To which objects can you assign a user status? Note: There are 3 correct answers to this question.
- A. Maintenance planner groups
- B. Work centers
- C. Technical objects
- D. Notifications
- E. Maintenance orders and operations
Answer: C,D,E
NEW QUESTION 52
Based on the SAP Activate methodology, which activities must you perform in the Explore phase? Note:
There are 2 correct answers to this question.
- A. Use the Starter system to demonstrate SAP Best Practices processes
- B. Configure the organizational structure and chart of accounts in the system
- C. Use the Quality system to demonstrate SAP Best Practices processes
- D. Conduct the Fit-to-Standard workshops to enable customers and identify gaps
Answer: A,D
NEW QUESTION 53
Which types of datasets are required for predictive scenarios? Note: There are 2 correct answers to this question.
- A. Active Dataset
- B. Apply Dataset
- C. Training Dataset
- D. Testing Dataset
Answer: A,C
NEW QUESTION 54
What can you use the View Browser app to do?
- A. Create, edit, and delete CDS views
- B. Launch analytic cloud stories
- C. Get a list of all available analytical CDS views and their artifacts
- D. Display custom SAP views irrespective of draft or released status
Answer: C
NEW QUESTION 55
Your organization has implemented the Improvement Maintenance (4VT) scope item. What is the business benefit of implementing this solution?
- A. It improves cost awareness and asset performance
- B. It simplifies the day to day work for maintenance technicians
- C. It improves the execution of maintenance plans
- D. It enables the integration of maintenance projects with maintenance orders
Answer: A
NEW QUESTION 56
You want to authenticate employees in SAP Cloud Identity. In which app can you download a .CSV file with the list of users?
- A. Maintain business users
- B. Maintain catalog roles
- C. Maintain communication users
- D. Maintain business roles
Answer: D
NEW QUESTION 57
What are the prerequisites for using the SAP Fiori Test Your Processes app? Note: There are 2 correct answers to this question.
- A. SAP Best Practices are activated in the quality system
- B. The quality system is connected to the Test Execution Service on SAP Cloud Platform
- C. The test scripts are uploaded in the productive system
- D. The productive system is connected to the implementation landscape
Answer: A,B
NEW QUESTION 58
A customer needs detailed customization to the standard forms and email templates. What solution should the consultant propose?
- A. Use the corresponding configuration items to modify elements of the form template
- B. Create a custom UI with the Custom Fields and Logic app
- C. Use the Adobe Livecycle Designer tool to edit a standard template
- D. Use the Output Management apps to customize a standard template
Answer: C
NEW QUESTION 59
For which of the following objects can you set up a bi-directional synchronization between SAP S/4HANA Cloud and asset central foundation?
- A. Equipment master
- B. Fixed asset master
- C. Material master
- D. Function location master
Answer: A
NEW QUESTION 60
Which of the following are outcomes of the Fit-to-Standard workshop? Note: There are 3 correct answers to this question.
- A. Solution impact on business processes
- B. Identification of source code changes
- C. Expert configuration definition
- D. Extensibility solutions to close gaps
- E. Finalized scope and integration requirements
Answer: A,C,E
NEW QUESTION 61
Based on the SAP Activate methodology, which of the following tests are formal, and therefore must be documented during implementation? Note: There are 2 correct answers to this question.
- A. Unit test
- B. Business process test
- C. Integration test
- D. String test
Answer: B,C
NEW QUESTION 62
What are the prerequisites when setting up a time-based strategy plan? Note: There are 2 correct answers to this question.
- A. Assign maintenance strategies to maintenance plan items
- B. Assign maintenance packages to task list operations
- C. Assign maintenance strategies to task list headers
- D. Assign various time-based cycles to the planning data of a maintenance plan
Answer: A,C