NEW QUESTION # 55
How can you grant individual authorization for WBS elements and networks?

  • A. Activate access control lists (ACL) for the user master record.
  • B. Define a user status to lock the business transaction Update Project.
  • C. Activate access control lists (ACL) for the project profile and the network profile.
  • D. Set the system status to "Lock Master Data".

Answer: C


NEW QUESTION # 56
The various work packages in the project are described as individual______________. Choose the correct answer.

  • A. Activities
  • B. Project definitions
  • C. Tasks
  • D. WBS elements

Answer: D


NEW QUESTION # 57
Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?

  • A. Double the work of each internal activity, one after another, in the project Builder.
  • B. Use mass change within the project Builder (CJ20N).
  • C. Use mass change (CNMASS) in the project system.
  • D. Double the capacity in the work center.

Answer: C

Explanation:
Mass change (CNMASS) is a powerful tool that allows you to change multiple fields in multiple objects at once. You can use it to change fields in project definitions, WBS elements, networks, activities, milestones, and PRTs." Reference: 3


NEW QUESTION # 58
You want to exchange data between SAP Project System and Microsoft What interface do you use?

  • A. The catalog interface.
  • B. you do not need and interface. You can exchange data using object link.
  • C. No interface to Microsoft Project is available.
  • D. The EPS interface (External Project Software).

Answer: D

Explanation:
"The EPS interface enables you to exchange data between SAP Project System and Microsoft Project." Reference: 2


NEW QUESTION # 59
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question

  • A. Goods receipt into unvaluated project stock
  • B. Goods receipt into valuated project stock
  • C. Recording of external services in the service entry sheet
  • D. Goods receipt of a non-stock item

Answer: C,D


NEW QUESTION # 60
Which statement is valid regarding networks?

  • A. A network activity can be assigned to several WBS elements
  • B. Relationships can be used to connect activities of different networks
  • C. A network can be activity-account-assigned and header-account-assigned
  • D. Material components can be assigned to activity elements

Answer: B

Explanation:
One statement that is valid regarding networks is that relationships can be used to connect activities of different networks. Networks are structural elements of a project that represent processes or operations within a project. Networks consist of various activities that represent tasks or partial tasks within a network. Relationships are logical connections between activities or networks that define the sequence or dependency of their execution. Relationships can be used to connect activities of different networks in order to model complex processes that span across multiple networks. For example, you can use a finish-start relationship to indicate that an activity in one network cannot start until an activity in another network is finished. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 61
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

  • A. The manual hierarchical revenue planning will be displayed only if expert mode is activated
  • B. The manual hierarchical revenue planning has no reference to cost elements
  • C. Cost element reports can display costs but not revenues
  • D. Cost element reports display integrated planning only

Answer: B

Explanation:
The reason why the cost element report for planned revenues does not show any revenues at all is that the manual hierarchical revenue planning has no reference to cost elements. Manual hierarchical revenue planning is a type of revenue planning that allows you to plan revenues for WBS elements manually without using sales documents. Manual hierarchical revenue planning does not use cost elements as a basis for planning, but uses revenue elements instead. Revenue elements are a set of data that define the characteristics and properties of a revenue type. Cost element reports can only display data that is based on cost elements, not revenue elements. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 62
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. The scheduling type of a subnetwork is always copied from the superior network
  • B. Maintenance orders can be defined as sub-network
  • C. A subnetwork cannot be defined for a superior subnetwork.
  • D. Subnetworks must be scheduled separately from the superior network

Answer: A

Explanation:
One statement that describes subnetworks is that the scheduling type of a subnetwork is always copied from the superior network. A subnetwork is a network that covers only part of a project and is linked in relationships with other subnetworks in the same project. A subnetwork can be used to refine and detail your networks as planning progresses. The scheduling type is a parameter that determines how the dates of activities and networks are calculated based on their dependencies and constraints. The scheduling type of a subnetwork is always copied from the superior network when creating or changing a subnetwork. The scheduling type of a subnetwork cannot be changed independently from the superior network. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/f373bb53707db44ce10000000a174cb4.html


NEW QUESTION # 63
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

  • A. Duration
  • B. Profit center
  • C. Activity type
  • D. Work

Answer: A,C

Explanation:
To determine the planned costs for an internally processed activity, you need the duration and activity type data. The duration is the time required to complete the activity. The activity type is a classification of activities according to their functions or characteristics. The system calculates the planned costs for an internally processed activity based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 64
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the project definition
  • B. In the WBS element
  • C. In the network activity
  • D. In the material master

Answer: A


NEW QUESTION # 65
The various work packages in the project are described as individual______________. Choose the correct answer.

  • A. Project definitions
  • B. Tasks
  • C. WBS elements
  • D. Activities

Answer: D

Explanation:
The various work packages in the project are described as individual activities. Activities are the smallest units of a project that can be planned, executed, and controlled. Activities can be assigned to one or more WBS elements in a project. Activities can also be linked to each other by relationships to define the sequence and dependencies of the work packages. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html


NEW QUESTION # 66
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.

  • A. Create an external activity in a network.
  • B. Create a service milestone.
  • C. Create a service activity in a network.
  • D. Assign a purchase order for external processing to the project definition.

Answer: A,C

Explanation:
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers." Reference: 4


NEW QUESTION # 67
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
  • B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
  • C. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
  • D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

Answer: B

Explanation:
To solve the problem of the system not preventing their project managers from exceeding their budgets, you have to activate availability control in the assigned budget profile and define the tolerance limits in customizing. The budget profile is a parameter that defines the basic settings for budgeting in your project, such as whether availability control is active or not. The tolerance limits are values that specify how much deviation from the budget is allowed before the system issues warnings or error messages. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 68
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Network type
  • B. Project profile
  • C. Parameters for the network type
  • D. Network profile

Answer: C


NEW QUESTION # 69
How can you grant individual authorization for WBS elements and networks?

  • A. Activate access control lists (ACL) for the user master record.
  • B. Define a user status to lock the business transaction Update Project.
  • C. Activate access control lists (ACL) for the project profile and the network profile
  • D. Set the system status to "Lock Master Data".

Answer: C

Explanation:
To grant individual authorization for WBS elements and networks, you have to activate access control lists (ACL) for the project profile and the network profile. Access control lists are a feature that allows you to control access to project objects, such as WBS elements and networks, based on user-specific authorization objects. You can use access control lists to define which users can create, change, display, or delete project objects. The project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. The network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. You have to activate access control lists for both the project profile and the network profile in Customizing in order to use them for WBS elements and networks. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 70
Resources
How are capacity requirements determined?

  • A. Using the control key of an activity.
  • B. Independent of scheduling and according to the capacity planner group.
  • C. Using scheduling and the capacity category.
  • D. Using scheduling and distribution key.

Answer: D


NEW QUESTION # 71
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

  • A. Actual revenue is posted via a billing document created from a sales order
  • B. Actual revenue is posted via a billing plan assigned to a WBS element
  • C. Planned revenue can be transferred from a sales quotation
  • D. Planned revenue requires a sales order assigned to a WBS element

Answer: B,C


NEW QUESTION # 72
......


To prepare for the SAP C_TS412_2021 certification exam, candidates are advised to have a good understanding of SAP S/4HANA Project Systems and to have hands-on experience with the software. SAP offers a range of training courses and resources to help candidates prepare for the certification exam, including classroom training, e-learning courses, and certification study materials.


SAP C-TS412-2021 certification exam is designed for professionals who want to prove their knowledge and skills in SAP S/4HANA Project Systems. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is intended for application associates who are responsible for managing and implementing SAP S/4HANA Project Systems. It is a globally recognized certification that validates the candidate's expertise in the field and enhances their career prospects.

 