CompTIA PK0-004 Exam Syllabus Topics:

TopicDetails

Project Basics - 36%

Summarize the properties of a project.1. Temporary2. Start and finish
3. Unique
4. Reason/purpose
5. Project as part of a program
6. Project as part of a portfolio
Classify project roles and responsibilities.1.Sponsor/champion
  1. Approval authority
  2. Funding
  3. Project charter
  4. Baseline
  5. High-level requirements
  6. Control
  7. Marketing
  8. Roadblocks
  9. Business case/justification
2.Project manager
  1. Manage team, communication, scope, risk, budget, and time
  2. Manage quality assurance
  3. Responsible for artifacts
3.Project coordinator
  1. Support project manager
  2. Cross-functional coordination
  3. Documentation/ administrative support
  4. Time/resource scheduling
  5. Check for quality
4.Stakeholder
  1. Vested interest
  2. Provide input and requirements
  3. Project steering
  4. Expertise
5.Scheduler
  1. Develop and maintain project schedule
  2. Communicate timeline and changes
  3. Reporting schedule performance
  4. Solicit task status from resources
6.Project team
  1. Contribute expertise to the project
  2. Contribute deliverables according to schedule
  3. Estimation of task duration
  4. Estimation of costs and dependencies
7.Project Management Office (PMO)
  1. Sets standards and practices for organization
  2. Sets deliverables
  3. Provides governance
  4. Key performance indicators and parameters
  5. Provides tools
  6. Outlines consequences of non-performance
  7. Standard documentation/templates
  8. Coordinate resources between projects





Compare and contrast standard project phases.1.Initiation
  1. Project charter
  2. Business case
  3. High-level scope definition
  4. High-level risks
2.Planning
  1. Schedule
  2. Work breakdown structure
  3. Resources
  4. Detailed risks
  5. Requirements
  6. Communication plan
  7. Procurement plan
  8. Change management plan
  9. Budget
3.Execution
  1. Deliverables
4.Monitor and control
  1. Risks/issues log
  2. Performance measuring and reporting
  3. Quality assurance/governance
  4. Change control
  5. Budget
5.Closing
  1. Transition/integration plan
  2. Training
  3. Project sign off
  4. Archive project documents
  5. Lessons learned
  6. Release resources
  7. Close contracts


Identify the basics of project cost control.1. Total project cost2. Expenditure tracking
3. Expenditure reporting
4. Burn rate
5. Cost baseline/budget
  1. Plan vs. actual
Identify common project team organizational structures.1.Functional
  1. Resources reporting to functional manager
  2. Project manager has limited or no authority
2.Matrix
  1. Authority is shared between functional managers and project managers
  2. Resources assigned from functional area to project
  3. Project manager authority ranges from weak to strong
3.Projectized
  1. Project manager has full authority
  2. Resources report to project manager
  3. Ad hoc resources
Given a scenario, execute and develop project schedules.1.Work breakdown structure
2.Scheduling activities
  1. Determine tasks
  2. Determine task start/finish dates
  3. Determine activity/task durations
  4. Determine milestones
  5. Set predecessors
  6. Set dependencies
  7. Sequence tasks
  8. Prioritize tasks
  9. Determine critical path
  10. Allocate resources
  11. Set baseline
  12. Set quality gates
  13. Set governance gates
  14. Client sign off
  15. Management approval
  16. Legislative approval
Identify the basic aspects of the Agile methodology.1. Readily adapt to new/ changing requirements2. Iterative approach
3. Continuous requirements gathering
4. Establish a backlog
5.Burndown charts
6. Continuous feedback
7. Sprint planning
8. Daily standup meetings/ SCRUM meetings
9. SCRUM retrospective
10. Self-organized and self-directed teams
Explain the importance of human resource, physical resource, and personnel management.1.Resource management concepts
  1. Shared resources
  2. Dedicated resources
  3. Resource allocation
  4. Resource shortage
  5. Resource overallocation
  6. Low quality resources
  7. Benched resources
  8. Interproject dependencies
  9. Interproject resource contention
2.Personnel management
  1. Team building
  2. Trust building
  3. Team selection
  4. Skill sets
  5. Remote vs. in-house
  6. Personnel removal/replacement
  7. Communication issues
  8. Conflict resolution
  9. Smoothing
  10. Forcing
  11. Compromising
  12. Confronting
  13. Avoiding
  14. Negotiating

Project Constraints - 17%

Given a scenario, predict the impact of various constraint variables and influences throughout the project.1.Common constraints
  1. Budget
  2. Scope
  3. Deliverables
  4. Quality
  5. Environment
  6. Resources
  7. Requirements
  8. Scheduling
2.Influences
  1. Change request
  2. Scope creep
  3. Constraint reprioritization
  4. Interaction between constraints
  5. Stakeholders/sponsors/management
  6. Other projects
Explain the importance of risk strategies and activities.1.Strategies
  1. Accept
  2. Mitigate
  3. Transfer
  4. Avoid
  5. Exploit
2.Risk activities
  1. Identification
  2. Quantification
  3. Planning
  4. Review
  5. Response
  6. Register
  7. Prioritization
  8. Communication

Communication & Change Management - 26%

Given a scenario, use the appropriate communication method.1.Meetings
  1. Kick-off meetings
  2. Virtual vs. in-person meetings
  3. Scheduled vs. impromptu meetings
  4. Closure meetings
2. Email
3. Fax
4. Instant messaging
5. Video conferencing
6. Voice conferencing
7.Face-to-face
8.Text message
9. Distribution of printed media
10. Social media
Compare and contrast factors influencing communication methods.1. Language barriers2. Time zones/geographical factors
3. Technological factors
4. Cultural differences
5.Interorganizational differences
6.Intraorganizational differences
7. Personal preferences
8. Rapport building/relationship building
9. Tailor method based on content of message
10. Criticality factors
11. Specific stakeholder communication requirements
  1. Frequency
  2. Level of report detail
  3. Types of communication
  4. Confidentiality constraints
  5. Tailor communication style
Explain common communication triggers and determine the target audience and rationale.1. Audits2. Project planning
3. Project change
4. Risk register updates
5. Milestones
6. Schedule changes
7. Task initiation/completion
8. Stakeholder changes
9. Gate reviews
10. Business continuity response
11. Incident response
12. Resource changes
Given a scenario, use the following change control process within the context of a project.1.Change control process
  1. Identify and document
  2. Evaluate impact and justification
  3. Regression plan (Reverse changes)
  4. Identify approval authority
  5. Obtain approval
  6. Implement change
  7. Validate change/quality check
  8. Update documents/audit documents/version control
  9. Communicate throughout as needed
2. Types of common project changes
  1. Timeline change
  2. Funding change
  3. Risk event
  4. Requirements change
  5. Quality change
  6. Resource change
  7. Scope change
Recognize types of organizational change.1. Business merger/acquisition2. Business demerger/split
3. Business process change
4. Internal reorganization
5. Relocation
6. Outsourcing

Project Tools & Documentation - 21%

Compare and contrast various project management tools.1.Project scheduling software
2.Charts
  1. Process diagram
  2. Histogram
  3. Fishbone
  4. Pareto chart
  5. Run chart
  6. Scatter chart
  7. Gantt chart
3.Dashboard/status report
4.Knowledge management tools
  1. Intranet sites
  2. Internet sites
  3. Wiki pages
  4. Vendor knowledge bases
  5. Collaboration tools
5.Performance measurement tools
  1. Key performance indicators
  2. Key performance parameters
  3. Balanced score card
6.SWOT analysis
7. Responsible, Accountable, Consulted, Informed (RACI) Matrix

Given a scenario, analyze project centric documentation.1. Project charter2. Project management plan
3. Issues log
4. Organizational chart
5. Scope statement
6. Communication plan
7.Project schedule
8.Status report
9.Dashboard information
10.Action items
11.Meeting agenda/meeting minutes


CompTIA PK0-004 certification exam is a popular certification offered by CompTIA for professionals who wish to enhance their project management skills. CompTIA Project+ Certification Exam certification exam is specifically designed to test the knowledge and skills required to manage projects effectively. CompTIA Project+ Certification Exam certification exam covers various aspects of project management, including project initiation, planning, execution, monitoring and control, and project closure.

 

NEW QUESTION # 262
Which of the following is the BEST reason to conduct regular risk reviews?

  • A. Risk reviews ensure stakeholders take action on assigned items.
  • B. Risk reviews must be reported in status updates.
  • C. Risk reviews allow for the identification of response strategies.
  • D. Risk reviews can keep personnel on track with their assigned tasks.

Answer: C


NEW QUESTION # 263
A project stakeholder is disappointed the team was not included in some key decisions. This resulted in extra discussions and rework. Which of the following documents should the project manager review and update to resolve this situation?

  • A. RACI chart
  • B. Collaboration site
  • C. Wiki page
  • D. Dashboard

Answer: A


NEW QUESTION # 264
The project manager needs to motivate the team; however, there is an insufficient budget for awards.
Which of the following motivating agents is the MOST appropriate option the project manager can utilize?

  • A. Extend the timeline
  • B. Provide additional responsibility
  • C. Reduce the workload
  • D. Replace resources

Answer: B


NEW QUESTION # 265
Which of the following is an example of a project?

  • A. Presenting a scripted workshop at an organization's three locations
  • B. Conducting semi-annual blood drives at an organization
  • C. Implementing a health awareness program at an organization
  • D. Purchasing pedometers from local retail stores for employees

Answer: C


NEW QUESTION # 266
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success.
Which of the following risk strategies should the project manager adopt?

  • A. Acceptance
  • B. Avoidance
  • C. Mitigation
  • D. Exploitation

Answer: D

Explanation:
References:
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 239


NEW QUESTION # 267
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?

  • A. RFO
  • B. RFI
  • C. RFQ
  • D. RFP

Answer: B

Explanation:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300


NEW QUESTION # 268
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?

  • A. A list of decomposed activities
  • B. A list of realized risks
  • C. A sequenced list of project tasks
  • D. A document describing agreed-upon communication methods

Answer: B

Explanation:
References:
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240


NEW QUESTION # 269
Everyone on the team agrees with a change request, and the team proceeds with the implementation. Which of the following steps is missing from the identified process?

  • A. Formal approval
  • B. Impact justification
  • C. Identify and document
  • D. Quality check

Answer: A


NEW QUESTION # 270
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A.
Task D and E start after Task C.
If Task A starts on December 15, which of the following is the anticipated start date for Task D?

  • A. December 19
  • B. December 21
  • C. December 18
  • D. December 22
  • E. December 20

Answer: C


NEW QUESTION # 271
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time?

  • A. Resource smoothing
  • B. Throttling
  • C. Crashing
  • D. Resource leveling

Answer: C

Explanation:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170


NEW QUESTION # 272
A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?

  • A. Backlog
  • B. Kickoff
  • C. Retrospective
  • D. Standup

Answer: D

Explanation:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306


NEW QUESTION # 273
In a highway construction project, the project team has identified the need to utilize additional land for staging equipment.
After documenting the change request, which of the following should be accomplished NEXT?

  • A. Identify the approval authority
  • B. Obtain approval
  • C. Audit the documentation
  • D. Communicate with the stakeholders

Answer: A


NEW QUESTION # 274
A project manager creates a Pareto chart based on the table below:

Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and faulty installation?

  • A. To take corrective action and identify the causes resulting in the highest number of issues
  • B. To take corrective action and identify the effects resulting in the highest number of issues
  • C. To take preventive action and identify and frequencies resulting in the highest number of issues
  • D. To take preventive action and identify the causes resulting in the highest number of issues

Answer: D


NEW QUESTION # 275
An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:

  • A. an MOU.
  • B. an SLA.
  • C. an RFP.
  • D. an NDA.

Answer: D

Explanation:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 302


NEW QUESTION # 276
A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

  • A. Change request
  • B. SOW
  • C. SLA
  • D. RFP

Answer: B

Explanation:
Explanation/Reference:
Explanation
"If you're working with vendors to perform some or all of the work of the project, it's critical that they know exactly what you are asking them to do. The statement of work (SOW) details the goods or services you want to procure. In many respects it's similar to the project scope statement, except that it focuses on the work being procured. It contains the project description, major deliverables, success criteria, assumptions, and constraints"
Excerpt From: Kim Heldman. "CompTIA Project+ Study Guide." iBooks.


NEW QUESTION # 277
A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project's success?

  • A. Decrease staff
  • B. Update the WBS
  • C. Increase the budget
  • D. Reduce the scope

Answer: B


NEW QUESTION # 278
A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?

  • A. Project schedule
  • B. Budget
  • C. Meeting minutes
  • D. Issue log

Answer: D


NEW QUESTION # 279
A project manager determines deliverables are not meeting customer specifications. During which of the following project phases is this determination MOST likely to happen?

  • A. Monitor and control
  • B. Planning
  • C. Execution
  • D. Closing

Answer: A

Explanation:
Explanation/Reference:


NEW QUESTION # 280
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the fallowing documents would contain these items?

  • A. Requirements document
  • B. Business case
  • C. Project timeline
  • D. Task plan

Answer: B


NEW QUESTION # 281
Company A recently partnered with Company B.
Over the past few months, multiple teams have been working to refine internal processes to deliver products in a more timely manner.
If the effort is successful, which of the following will MOST likely occur?

  • A. Relocation
  • B. Outsourcing
  • C. Demerger
  • D. Reorganization

Answer: D


NEW QUESTION # 282
......