Question 1
A project lead has the following requirements for a new design:
* When there is a deficit in the quantity of materials to be delivered by the supplier in a purchase order, an event will be triggered in S/4HANA Cloud by a periodic background job.
* The business event will be sent to SAP Event Mesh. A custom process will then be started in an on-premise system.
* The IT staff will have to set up several different scenarios using different on-premise systems.
The project lead wants an SAP BTP solution that provides guided workflows with assignable tasks to members of the IT staff to help them set up the scenarios.
As the solution architect, which of the following do you recommend?
* When there is a deficit in the quantity of materials to be delivered by the supplier in a purchase order, an event will be triggered in S/4HANA Cloud by a periodic background job.
* The business event will be sent to SAP Event Mesh. A custom process will then be started in an on-premise system.
* The IT staff will have to set up several different scenarios using different on-premise systems.
The project lead wants an SAP BTP solution that provides guided workflows with assignable tasks to members of the IT staff to help them set up the scenarios.
As the solution architect, which of the following do you recommend?
Correct Answer: A
Question 2
According to the SAP Integration Solution Advisory Methodology, the integration architect is responsible for which of the following activities?
Correct Answer: D
Question 3
A customer wants to design and build a mission critical application:
* The app will undergo frequent adjustments because business and legal changes will occur often.
* The application must be always ready for deployment to production.
* The deployment to production will be done manually by the IT department.
* Changes to the application code must be merged smoothly and easily so that the code remains stable.
As a solution architect, which SAP BTP solution best meets the customer requirements?
* The app will undergo frequent adjustments because business and legal changes will occur often.
* The application must be always ready for deployment to production.
* The deployment to production will be done manually by the IT department.
* Changes to the application code must be merged smoothly and easily so that the code remains stable.
As a solution architect, which SAP BTP solution best meets the customer requirements?
Correct Answer: C
Question 4
The DevOps / Site Reliability Team has a Question: for you. Over the course of the last month, several trust certificates have expired for several SAP BTP destinations, which has in turn occupied a significant portion of their time reinstalling. They wish to be informed before the certificate expires and to have a workflow triggered automatically.
As a solution architect, which SAP BTP service would you recommend (see attached diagram >)?

As a solution architect, which SAP BTP service would you recommend (see attached diagram >)?

Correct Answer: C
Question 5
As a solution architect, you are asked for your opinion on an optimal integration. You are told that the data resides in two places, SAP S/4HANA (on- premise) and third party APIs. You are also told the following requirements:
* Periodically read the data from both systems, perform several transformations of the data, and forward the results to a business partner.
* Monitoring is to be done by a dedicated group from IT with SAP products.
* Maintenance of the integration part has a small budget, limited time, and limited resources.
Which of the following solutions would you recommend as optimal for the design?
* Periodically read the data from both systems, perform several transformations of the data, and forward the results to a business partner.
* Monitoring is to be done by a dedicated group from IT with SAP products.
* Maintenance of the integration part has a small budget, limited time, and limited resources.
Which of the following solutions would you recommend as optimal for the design?
Correct Answer: C