Question 1
In which phase should you create a data migration strategy (L0) during a selective data transition?
Correct Answer: B
Question 2
What tool do you use to configure an SAP Business Suite on-premise solution?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 3
Which collaboration features can SAP Activate Jam users access?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,D
Question 4
How many countries can be activated at a time?
Correct Answer: B
Question 5
Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,D
Question 6
What is the key characteristic of Agile project delivery?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 7
What solution operation framework can customers use to create a joint business and IT organisation that will secure transparency and efficiency of SAP implementation.
Correct Answer: C
Question 8
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 9
What are examples of some information captured in the Digital Discovery Assessment?
Correct Answer: A,C
Question 10
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 11
Which activities are part of the Design and Configuration application of the SAP Activate methodology?
There are 2 correct answers to this question
There are 2 correct answers to this question
Correct Answer: B,C
Question 12
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 13
How can the project manager help to keep momentum in the project and help to keep the customer involved?
Correct Answer: B,C
Question 14
Which accelerator can help you document the detailed design of solution extensions? Please choose the correct answer.
Correct Answer: D