Question 1
Your customer upgraded a system to SAP S/4HANA for test reasons.
You receive feedback from the business department that while opening and closing posting periods, the systems asks for a customizing request.
What is the reason?
Please choose the correct answer.
Response:
You receive feedback from the business department that while opening and closing posting periods, the systems asks for a customizing request.
What is the reason?
Please choose the correct answer.
Response:
Correct Answer: C
Question 2
Which characteristics of the ACDOCP planning table distinguish it from most other SAP S/4HANA tables?
Note: There are 2 correct answers to this question.
Response:
Note: There are 2 correct answers to this question.
Response:
Correct Answer: C,D
Question 3
Your system currently does NOT use business partners (BP). The master data for suppliers and vendors and the defined account groups are NOT connected and are handled by separate departments.
When preparing for integration, what do you have to create?
Response:
When preparing for integration, what do you have to create?
Response:
Correct Answer: A
Question 4
Your customer is implementing a new installation of SAP S/4HANA.
Which of the following technical components must be installed?
Response:
Which of the following technical components must be installed?
Response:
Correct Answer: A
Question 5
Which of the following are key benefits of SAP S/4HANA?
Note: There are 2 correct answers to this question.
Response:
Note: There are 2 correct answers to this question.
Response:
Correct Answer: A,B
Question 6
Where can you find the automatic write-off program to close unpaid customer balances?
Response:
Response:
Correct Answer: A
Question 7
You perform a direct activity allocation. Which database tables are updated?
Note: There are 2 correct answers to this question.
Response:
Note: There are 2 correct answers to this question.
Response:
Correct Answer: A,D
Question 8
You migrate a system from SAP ERP with classic G/L to SAP S/4HANA.
Which activities must you perform in the productive SAP S/4HANA system before the software is installed?
Note: There are 3 correct answers to this question.
Response:
Which activities must you perform in the productive SAP S/4HANA system before the software is installed?
Note: There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Question 9
You perform planning in SAP Business Planning and Consolidation for SAP S/4HANA.
Why do you retract the plan data from SAP Business Planning and Consolidation for SAP SI4HANA and return it to the standard planning tables?
Note: There are 2 correct.
Response:
Why do you retract the plan data from SAP Business Planning and Consolidation for SAP SI4HANA and return it to the standard planning tables?
Note: There are 2 correct.
Response:
Correct Answer: A,B