Question 1
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
Correct Answer: A,B
Question 2
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
Correct Answer: B,D,E
Question 3
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
Correct Answer: A,C,D
Question 4
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
Correct Answer: C,E
Question 5
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?
Correct Answer: C
Question 6
Which object is used to allocate the costs from a claim to the project structure?
Correct Answer: D