SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4 (C-TPLM22-64) Free Practice Test
Question 1
What are the two basic elements that SAP Project system provides for mapping the structures of projects?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
Question 2
Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 3
Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 4
Which of the following information regarding cost activity is not relevant for the calculation of planned costs?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 5
Which of the following determines the item category assigned in the sales documents?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,D
Question 6
What do you choose when creating a new network by copying an operative network?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Question 7
What are the different options available for project stock?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Question 8
How do you optimize cash flows to maximize project profits and reduce project costs?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 9
Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Question 10
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 11
Which account category is used for account assignment of orders, which includes network headers, network activities, maintenance orders, internal orders and manufacturing orders?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 12
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 13
In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 14
Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 15
Which function allows you to check consistency of the dates within the project structure with or without taking activities into account?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A