PMI Program Management Professional (PgMP) (PgMP) Free Practice Test

Question 1
You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

Correct Answer: C
Question 2
During a global health crisis, the senior leadership of a hospital system asked a program manager to evaluate a crucial clinical program due to uncertain patient needs and poor project component quality. What should the program manager do first?

Correct Answer: C
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 3
You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order.
What term describes the activities that can happen in any order?

Correct Answer: D
Question 4
Which of the following statements is most accurate about the critical path?

Correct Answer: C
Question 5
A program is behind schedule despite incremental benefits delivered regularly due to efforts by component projects. The program sponsor is concerned about potential cost overruns and further schedule slips. What should the program manager do to address the program sponsor's concerns?

Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 6
An infrastructure program has 20 projects. The first half of these projects incurred multiple change orders and failed to be completed on time. The program manager meets with the project managers to discuss lessons learned and to understand the challenges. During the meeting, the project managers complain that key risks and a lack of resources resulted in missing deadlines.
What should the program manager do to ensure that the remaining 10 component projects stay on track?

Correct Answer: C
Question 7
A program manager, who reports to a company's CIO, is responsible for managing a strategic initiative program. During a program review meeting, the CIO informs the program manager about potential budget cuts that would impact program resources, and urges the program manager to begin delivering benefits more quickly to continue the program.
What should the program manager do first?

Correct Answer: D
Question 8
During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?

Correct Answer: C
Question 9
A program had an issue because team members were not consistently adhering to agreed-upon procedures. Several team members stated that they thought the procedures were inadequate as documented so they improvised what they thought was a better solution. How can the program manager reduce the likelihood of this issue reoccurring?

Correct Answer: C
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 10
A program will generate revenue for several years after it ends. The program manager and the operations manager, who are accountable for managing the benefits after program closure, are in disagreement. The operations manager is concerned that information necessary for managing the processes and benefits after program closure will be unavailable. The program manager expresses that managing the benefits after program closure is not within the scope and must be managed through the scope management plan.
What should the program sponsor do?

Correct Answer: B
Question 11
A high-profile customer has a program dashboard set up for immediate access to the status of a key program. The customer reports that the reported status is incorrect. What should the program manager do?

Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 12
A program sponsor is determining whether to add another project to a program portfolio but is unsure if the project will align with organizational objectives. What should the program manager do to demonstrate the project's organizational alignment?

Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 13
Several program managers in an organization are looking for opportunities to establish continuous improvement. What should the program managers recommend to senior leadership?

Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 14
You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Correct Answer: A