Welcome to TestSimulate

Pass Your Next Certification Exam Fast!

Everything you need to prepare, learn & pass your certification exam easily.

365 days free updates. First attempt guaranteed success.

Peoplecert PRINCE2 Foundation (PC0-004) Free Practice Test

Question 1
Which does a Project Manager produce to define and control the work to be done?

Correct Answer: D
Question 2
Which describes risk appetite?

Correct Answer: B
Question 3
Which is a purpose of the Risk theme?

Correct Answer: B
Question 4
Which is an objective of the Initiating a Project process?

Correct Answer: A
Question 5
Which role is responsible for the management of a risk assigned to it?

Correct Answer: A
Question 6
Which is a true statement about time-driven controls?

Correct Answer: D
Question 7
Identify the missing words in the following sentence.
At an agreed frequency, a Team Manager will send a [ ? ] to the Project Manager.

Correct Answer: C
Question 8
What product identifies the management stages and other major control points in a project?

Correct Answer: A
Question 9
In what product should the quality criteria for a specialist product be recorded?

Correct Answer: A
Question 10
Which is a responsibility of a risk owner?

Correct Answer: D
Question 11
Which statement applies to Stage Plans?

Correct Answer: B
Question 12
Which activity takes place within the Managing a Stage Boundary process?

Correct Answer: A
Question 13
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

Correct Answer: D