Question 1
You have been asked to set up cost estimates for 10 different purchased items. Which two steps could be used to accomplish this task?

Correct Answer: C,E
Question 2
Identify two conditions that should be met at the same time for a Standard Operation to be called an Optional Operation.

Correct Answer: B,D
Question 3
The Plant Manager informs you that they have bought several machines for their manufacturing plant ABC.
The plant has been set up with a separate cost element set ABC in Manufacturing Cloud. You are requested to configure these machines in such a way that those are costed to the work order for which operations are performed on these machines.
Identify the correct setup that you will advise to the Plant Manager.

Correct Answer: D
Question 4
A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?

Correct Answer: E
Question 5
As a production supervisor, you require immediate access to critical shop floor execution systems to take action while on the go.
Which four work order related actions can be taken in the Manufacturing Supervisor mobile application?

Correct Answer: A,B,C,D
Question 6
You want to use a predefined Standard Operation in a Work Definition, but you also want to change the usage of the Standard Operation resource. Identify the setup required.

Correct Answer: C
Question 7
A Production Operator needs to load Work Order Transactions from an external system into Manufacturing Cloud.
Identify the correct sequence of tasks to be performed.

Correct Answer: C