Question 1
In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
Correct Answer: A,B,E
Question 2
Work order costs are computed based on material and resource transactions reported and the cost method of the product. In a manufacturing plant, the production operator has completed a work order WO-001 ensuring proper materials and resource transactions. The materials are costed and resources are defined with rates.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
Correct Answer: A
Question 3
In what three ways can you set the overcompletion tolerance for a subcomponent yield, so the job order can report the excess production completion?
Correct Answer: A,B,E
Question 4
A Manufacturing Engineer in a plant is creating an alternative manufacturing process for an item using its existing Work Definitions. After copying from the existing Work Definition WD1 to the alternative Work Definition WD2, the engineer finds that the operation items were not copied in the alternative manufacturing process WD2.
Identify the reason.
Identify the reason.
Correct Answer: C
Question 5
Your customer has defined the work definitions. They have created and saved a new version for the work definition and want to edit that work definition.
Which two attributes cannot be updated using the Edit Work Definition Details action?
Which two attributes cannot be updated using the Edit Work Definition Details action?
Correct Answer: B,C
Question 6
To reduce the subassembly stock with no impact on material planning of child components of the subassemblies stock, you need to modify the multilevel item structure of a product.
Identify the action that meets this requirement.
Identify the action that meets this requirement.
Correct Answer: A
Question 7
In your customer's manufacturing facility, different types of Movement Requests are created. Key manufacturing components are issued to the work orders form the manufacturing subinventory. The manufacturing subinventory receives its supplies form the Warehouse subinventory through automatically created Movement Requests.
Which type of Movement Requests should you use to fill the manufacturing subinventory form the Warehouse subinventory?
Which type of Movement Requests should you use to fill the manufacturing subinventory form the Warehouse subinventory?
Correct Answer: D