Oracle Manufacturing  and Maintenance Cloud 2019 Implementation Essentials (1Z1-1075) Free Practice Test

Question 1
In a Manufacturing Cloud post production support environment, a user wants to update some of the operations
in the work orders by using the Midpoint Scheduling feature. However, the user is unable to update any of the
orders.
Identify two reasons.

Correct Answer: C,D
Question 2
Identify three types of Item Quantities displayed in the Work Order History tab.

Correct Answer: B,C,E
Question 3
Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM)
and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order,
for a nonstocked item.

Correct Answer: D,E
Question 4
You are setting up Fusion Manufacturing to support Back-to-Back Fulfillment.
Identify an option that needs to be set for oracle Fusion Planning Central to plan back-to-back item
components and resources.

Correct Answer: B
Question 5
Your customer has multiple distribution centers and a few manufacturing plants. Plants make different items
with some overlap between them in terms of products manufactured. The distribution centers stock parts from
all plants. A Corporate Engineering team is responsible for centrally defining items and catalogues. This team
defines the items and sets the attributes for most parameters. The respective distribution centers and
manufacturing plants are allowed to change some attributes locally.
Identify two different ways of achieving this requirement.

Correct Answer: B,D
Question 6
The Plant Manager informs you that they have bought several machines for their manufacturing plant ABC.
The plant has been set up with a separate cost element set ABC in Manufacturing Cloud. You are requested to
configure these machines in such a way that those are costed to the work order for which operations are
performed on these machines.
Identify the correct setup that you will advise to the Plant Manager.

Correct Answer: D
Question 7
In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an
assembly have been defined as required.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and
compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the
cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting
in frozen type.

Correct Answer: A,B,E