Oracle EBS R12: Advanced Supply Chain Planning (1Z0-244) Free Practice Test
Question 1
Identify the element that does NOT belong to a Demand plan from Oracle Demand Planning.
Correct Answer: A
Question 2
Which two statements are correct about Use-Up Date in Engineering Change Order (ECO)?
Correct Answer: A
Question 3
The planning engine gives an exception message "Items with no activity." When does this exception appear?
Correct Answer: A
Question 4
Exhibit.

In the Distribution Network, the RDC5 and RDC6 Regional Distribution Centers source material from the DC3 Central Distribution Center.
The matrix in the Exhibit shows allocation for a supply quantity of 300 In the first allocation bucket.
Which Fair Share Allocation method was applied by the Distribution Plan?

In the Distribution Network, the RDC5 and RDC6 Regional Distribution Centers source material from the DC3 Central Distribution Center.
The matrix in the Exhibit shows allocation for a supply quantity of 300 In the first allocation bucket.
Which Fair Share Allocation method was applied by the Distribution Plan?
Correct Answer: C
Question 5
You have Late Replenishment for Sales Orders exceptions In a constrained plan. Which two methods could be used to find the cause of the lateness?
Correct Answer: C
Question 6
After a plan completes successfully, the planning SuperUser wants to be Informed If there Is a quantity excess of 7500 for a specific group of items. What would be your recommendation?
Correct Answer: C
Question 7
Exhibit.

You define a Supply Chain plan of type "Manufacturing Plan." In the Plan Options Main tab, you select Planned Items as "Demand schedule items and all sales orders" and select the Include Critical Components check box.
The Exhibit shows Bills of Material for Items A and
B. It also shows the settings for the Include Sales Order check box on the Plan Options Organizations tabbed page.
Item A has Demand Schedules and Sales Orders for Organizations Ml and M2. Item B has only Sales Orders for Organizations Ml and M2.
Which three statements are correct in the above plan scenario?

You define a Supply Chain plan of type "Manufacturing Plan." In the Plan Options Main tab, you select Planned Items as "Demand schedule items and all sales orders" and select the Include Critical Components check box.
The Exhibit shows Bills of Material for Items A and
B. It also shows the settings for the Include Sales Order check box on the Plan Options Organizations tabbed page.
Item A has Demand Schedules and Sales Orders for Organizations Ml and M2. Item B has only Sales Orders for Organizations Ml and M2.
Which three statements are correct in the above plan scenario?
Correct Answer: B,C,D
Question 8
You anticipate having a very large plan with many Items, Purchase Orders, and Sales Orders.
You want to plan at a detailed Item level as much as possible, but detailed Resource planning Is less Important.
Because your enterprise Is global. It Is Important to have the plan run In the shortest possible time.
Identify two aggregation settings that will help you achieve your goals.
You want to plan at a detailed Item level as much as possible, but detailed Resource planning Is less Important.
Because your enterprise Is global. It Is Important to have the plan run In the shortest possible time.
Identify two aggregation settings that will help you achieve your goals.
Correct Answer: B,C
Question 9
For Buy or Transfer orders, the Dock Date for Scheduled Receipts Is calculated as the
Correct Answer: D