Question 1
You are planning a meeting at the end of the Analysis phase that highlights the current health of the project, key milestones achieved, key deliverables completed, project level issues and risks, and the conditions of satisfaction assessment. This meeting will be the 'sign-off' of the Analysis phase.
Which Sure Step document do you prepare for this meeting?
Which Sure Step document do you prepare for this meeting?
Correct Answer: D
Question 2
Your company is preparing a proposal for a large and complex implementation that will require significant customizations in an enterprise organization. One of the elements that you plan to address is testing and creating a test plan. When is the best time to create a high-level test plan that includes the general standards and procedures that must be followed when conducting software testing and validation?
Correct Answer: A
Question 3
A prospective customer asks your sales person to prove that the proposed solution supports the specific
industry requirements. You need to ensure due-diligence is achieved.
What should you recommend?
Choose the 2 that apply.
industry requirements. You need to ensure due-diligence is achieved.
What should you recommend?
Choose the 2 that apply.
Correct Answer: C,D
Question 4
You are managing a complex, multisite project under a fixed price contract. Your customer wants to refine the project scope. You agree that the changes are appropriate, but believe that they constitute a major change that increases the project scope.
What should you do?
What should you do?
Correct Answer: C
Question 5
You decide that a rapid implementation approach is appropriate for your current project. How detailed should the scope documentation be for this type of engagement?
Correct Answer: A
Question 6
You advise your customer that it is important to start identifying internal resources for the identified project
roles.
Which skills are essential for a key user profile?
Choose the 2 that apply.
roles.
Which skills are essential for a key user profile?
Choose the 2 that apply.
Correct Answer: A,D
Question 7
You are determining the contract type for a new engagement. Based on the available diagnostic information, you come to the following conclusions:
-
There is uncertainty about a majority of the requirements
-
There is a significant gap between a large set of requirements and your Microsoft Dynamics solution
-
Your project team is not familiar with the customers's industry
-
Your customer is not familiar with implementation projects and business software. Which contract type should you recommend?
-
There is uncertainty about a majority of the requirements
-
There is a significant gap between a large set of requirements and your Microsoft Dynamics solution
-
Your project team is not familiar with the customers's industry
-
Your customer is not familiar with implementation projects and business software. Which contract type should you recommend?
Correct Answer: D
Question 8
You collaborated with the Solution Sales team to strategize how to execute a Business CaseAssessment. Which customer benefits do you realize when you execute a Business Case Assessment?
Choose the 2 that apply.
Choose the 2 that apply.
Correct Answer: B,C
Question 9
You manage a project with a Standard Project Type approach. The Analysis phase is closed and your team is engaged in design activities. The development consultant reports the technical designs are complete and wants to begin the development activities early.
What should you do?
What should you do?
Correct Answer: B
Question 10
Sure Step provides multiple ways to manage project documents. Which options allow you to collaborate more effectively and efficiently?
Choose the 2 that apply.
Choose the 2 that apply.
Correct Answer: B,D