ISTQB Certified Tester Advanced Level - Test Manager (CTAL-TM_001) Free Practice Test
Question 1
A car rental company offers discounts to its customers based on a number of factors, including booking history, length of membership and type of car being booked. An update to the rental application is under test, with test cases written that specifically address a documented product risk covering discount calculation.
Although the risk impact was analysed as high, the likelihood was given as low, as there had been no known changes to the calculation rules. However, during test execution some discount calculations were incorrect and investigation showed that code changes had been made that impacted the discount algorithms. As a result, the likelihood was increased to high by the risk management team.
Which would be the BEST measure to take to respond to the current situation?
Although the risk impact was analysed as high, the likelihood was given as low, as there had been no known changes to the calculation rules. However, during test execution some discount calculations were incorrect and investigation showed that code changes had been made that impacted the discount algorithms. As a result, the likelihood was increased to high by the risk management team.
Which would be the BEST measure to take to respond to the current situation?
Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 2
Which testing metric identifies defect density?
Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 3
As the Test Manager working for a company developing safety related software for defence equipment, you have been asked to consider how you can track test progress and report on the following:
1) Test cases adequately cover all requirements
2) Issues relating to safety critical vulnerabilities are being addressed in priority order
3) How much of the developed system has been exercised through testing What tools would help to achieve this?
SELECT ONE OPTION
1) Test cases adequately cover all requirements
2) Issues relating to safety critical vulnerabilities are being addressed in priority order
3) How much of the developed system has been exercised through testing What tools would help to achieve this?
SELECT ONE OPTION
Correct Answer: B
Question 4
You are reviewing the project's traceability matrix after the first cycle of testing. You have discovered that new requirements have been introduced and others have changed.
What should you do? [2]
What should you do? [2]
Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 5
As a Test Manager, which one of the following do you think is the MOST important reason for ensuring effective processes are in place for test monitoring and reporting?
SELECT ONE OPTION
SELECT ONE OPTION
Correct Answer: A
Question 6
You are writing the project test plan and are analysing the following risks in the project risk register:

Which would be the MOST appropriate test activities to mitigate the product risks?

Which would be the MOST appropriate test activities to mitigate the product risks?
Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 7
You have directed one of your testers to construct a "smoke test" to execute against new builds prior to starting formal testing. This is an example of which software development lifecycle activity?
[1]
[1]
Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 8
Which two of the following are considered to be advantages when specifying detailed test conditions?
a) They may influence development activities.
b) They form the basis for vertical traceability
c) They are suited to agile methodology
d) They can aid defect prevention
e) They are quick and easy to deliver
SELECT ONE OPTION
a) They may influence development activities.
b) They form the basis for vertical traceability
c) They are suited to agile methodology
d) They can aid defect prevention
e) They are quick and easy to deliver
SELECT ONE OPTION
Correct Answer: A
Question 9
You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''
Correct Answer: B
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).