EXIN Agile Scrum Foundation (ASF) Free Practice Test
Question 1
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?
What is the elapsed time required to complete the story?
Correct Answer: B
Question 2
Which statement describes Release Planning?
Correct Answer: B
Question 3
A team has eleven members spread over two locations across two time zones. One of the locations has six team members and the other team has five.
Where should a Scrum Master be located?
Where should a Scrum Master be located?
Correct Answer: A
Question 4
During the release planning meeting, it is difficult to agree on priorities.
Sales want to implement some new features to catch up with the competitors.
Marketing want to work on a mobile interface that can prove to be a competitive
differentiator.
Customer support want better logging and auditing capabilities to improve maintainability.
What should be done to set the priorities?
Sales want to implement some new features to catch up with the competitors.
Marketing want to work on a mobile interface that can prove to be a competitive
differentiator.
Customer support want better logging and auditing capabilities to improve maintainability.
What should be done to set the priorities?
Correct Answer: B
Question 5
Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan.
What term best describes the multi-level planning?
What term best describes the multi-level planning?
Correct Answer: B
Question 6
What is an "escaped defect"?
Correct Answer: A