CompTIA Project+ (PK0-003) Free Practice Test
Question 1
Which of the following is a common cause of resource conflicts?
Correct Answer: C
Question 2
In a functional structured organization, which of the following is a common cause of conflict with project team members?
Correct Answer: D
Question 3
Which of the following conflict resolution techniques involves one party overpowering another without regard to relationships within the group?
Correct Answer: B
Question 4
Determining how to communicate general project information with a globally dispersed team has created scheduling challenges. Which of the following would BEST remedy the situation?
Correct Answer: B
Question 5
Which of the following components of a project charter include identifying important milestones of the project?
Correct Answer: A
Question 6
In the planning phase of a project, which of the following activities is performed?
Correct Answer: C
Question 7
-- Exhibit -

-- Exhibit -
Click on the exhibit button. Which of the following is the critical path?

-- Exhibit -
Click on the exhibit button. Which of the following is the critical path?
Correct Answer: C
Question 8
A project manager has noticed low attendance at weekly meetings for a new project. Which of the following can the project manager do to improve meeting attendance?
Correct Answer: B
Question 9
The project team has just completed all of the design activities and will begin construction next week. Which of the following will the project manager do prior to beginning the construction work?
Correct Answer: A