Question 1
You are working for a large multinational organization and have been assigned to a new project.
For your new ML project you need to make sure you're managing data privacy and security as you're working with sensitive customer data.
What critical security issues do you need to make sure you address (Select all that apply.):
For your new ML project you need to make sure you're managing data privacy and security as you're working with sensitive customer data.
What critical security issues do you need to make sure you address (Select all that apply.):
Correct Answer: A,B,C,D
Question 2
Your team is tasked with selecting an algorithm for a supervised learning classification project.
Which algorithm might you choose?
Which algorithm might you choose?
Correct Answer: A
Question 3
Your team is working on an AI-enabled chatbot to be placed on the website. The goal of the chatbot is to be able to answer questions 24/7 to service clients around the globe. When evaluating your data you realize you don't have enough data to train the model.
What's the best course of action?
What's the best course of action?
Correct Answer: A
Question 4
You're working with a small inexperienced team on a new ML project. Choosing the best algorithm with the best settings given the training and test data is proving to be very hard for them. You lack the critical data science resources available on your team, and can't wait weeks until a data science resource becomes available to join your team.
What's your best course of action?
What's your best course of action?
Correct Answer: A
Question 5
Your model is going to be used for continuous monitoring of machinery, with need for continuous, instant model predictions. What's the most appropriate Model Operationalization approach?
Correct Answer: C
Question 6
A project manager is reviewing the performance of an AI model used for predictive analytics in sales. The model's accuracy is within acceptable limits; however, its precision is low.
What is the cause for the precision issue?
What is the cause for the precision issue?
Correct Answer: A
Question 7
You are establishing the data requirements for the project. Which of the following tasks is the least likely to impact data requirements?
Correct Answer: A
Question 8
A team is getting ready to begin working on a ML project. They need to build a data preparation pipeline and someone on the team suggests they reuse the same pipeline they created for their last project.
What's wrong with this suggestion?
What's wrong with this suggestion?
Correct Answer: D