Question 1
True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions?
Correct Answer: B
Question 2
Which statement below best describes the primary objective of the Sprint Review?
Correct Answer: D
Question 3
What happens when all committed items (requirements) are not completed at the end of the Sprint?
Correct Answer: B
Question 4
Which of the following statements best explains what the term Sprint means in Scrum?
Correct Answer: A
Question 5
What is the maximum time that Scrum recommends the team spend in the daily scrum (daily standup)?
Correct Answer: D
Question 6
The term Agile Development was first introduced in:
Correct Answer: C
Question 7
Which of the following is a role in the Scrum framework?
Correct Answer: A
Question 8
_____________ can change the priority of items in the _________ backlog at any time.
Correct Answer: D
Question 9
Who determines whether the development team has been assigned enough work in a Sprint?
Correct Answer: A