AEE Certified Energy Manager (CEM) (CEM) Free Practice Test

Question 1
In a chilled water thermal energy storage system, chilled water is stored at 4°C and used for supply water.
Chilled water return is 14°C. Calculate the storage capacity required to hold 50 GJ of thermal cooling. (The specific heat of water (C) is 4.2 kJ/kg-°C. Assume no system losses.)

Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 2
According to ISO 50001. when performing internal audits on the energy management system in an organization the internal auditor should do which of the following?
SELECT THE CORRECT ANSWER

Correct Answer: C
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 3
A 3 MW rated wind-powered turbine has a rotor diameter of 113 meters. What is the efficiency of the wind turbine at rated power if it is operating in wind power calculated at 8.6 MW? Assume an air density of 1.225 kg/m³.

Correct Answer: D
Question 4
What instrument determines flow rate by measuring pressure differential?

Correct Answer: D
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 5
Problems Caused by Harmonic Distortion
Which of the following problems is unlikely to be caused by harmonic distortion?
SELECT THE CORRECT ANSWER

Correct Answer: C
Question 6
Which motor parameter is the most difficult to determine accurately?
SELECT THE CORRECT ANSWER

Correct Answer: B
Question 7
Which of the following instruments is most useful for tracking long-term boiler performance?

Correct Answer: A
Explanation: Only visible for TestSimulate members. You can sign-up / login (it's free).
Question 8
If installed without ancillary equipment, photovoltaic power cells generate what type of power?

Correct Answer: C
Question 9
Using an interest rate of 15%, an energy project has a net-present value (NPV) of $3,500. Which statement is true about the project's internal rate of return (IRR)?

Correct Answer: A