Question 1
At Tiny Toys Ltd, business analyst Sophie has been employed to investigate and improve the invoicing process. To help her understand the data required in the system, she intends to request and review a sample of completed invoices.
What elicitation technique will she be using?
What elicitation technique will she be using?
Correct Answer: B
Question 2
A business analyst is in the process of validating a set of requirements produced for a new business initiative. The following needs to be agreed:
1) That the correct quality review procedures have been followed;
2) That the requirements are technically feasible;
3) That the requirements are compliant with business standards and
policies.
Who is responsible for agreeing these?
1) That the correct quality review procedures have been followed;
2) That the requirements are technically feasible;
3) That the requirements are compliant with business standards and
policies.
Who is responsible for agreeing these?
Correct Answer: D
Question 3
A project to improve internal IT help desk services at Worldco Bank, which operates internationally with offices in Europe, North and South America, has been initiated.
Laura, the chosen business analyst, is now faced with undertaking requirements elicitation from all the business heads spread across the Worldco territories.
Laura's initial focus in on quantitative information. Her manager is looking for the initial requirement set to be established quickly and cheaply.
Which approach SHOULD. Laura use for initial requirements elicitation?
Laura, the chosen business analyst, is now faced with undertaking requirements elicitation from all the business heads spread across the Worldco territories.
Laura's initial focus in on quantitative information. Her manager is looking for the initial requirement set to be established quickly and cheaply.
Which approach SHOULD. Laura use for initial requirements elicitation?
Correct Answer: C
Question 4
A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'.
What element of requirements management will offer this?
What element of requirements management will offer this?
Correct Answer: D
Question 5
A business analyst is working on a project seeking to deliver a new online booking system for a luxury conference center. The conference center includes three business areas:
* Customer Services
* Finance
* Regulation and Quality Assurance
The following list of requirements has been compiled from a range of elicitation activities:
1. The solution shall comply with the provisions of the General Data
Protection Regulation.
2. The receptionist shall be able to view the customer name, address
and telephone number.
3. The solution will be available to all users between 06:00hrs and
23:00hrs.
4. The customer shall be able to view available conference rooms for a
range of dates.
Which of the following represents the correct categorization of these requirements by business area?
* Customer Services
* Finance
* Regulation and Quality Assurance
The following list of requirements has been compiled from a range of elicitation activities:
1. The solution shall comply with the provisions of the General Data
Protection Regulation.
2. The receptionist shall be able to view the customer name, address
and telephone number.
3. The solution will be available to all users between 06:00hrs and
23:00hrs.
4. The customer shall be able to view available conference rooms for a
range of dates.
Which of the following represents the correct categorization of these requirements by business area?
Correct Answer: D
Question 6
The business analyst for a project has elicited, analysed and documented the requirements of the identified stakeholders; these have been validated and agreed.
A few days after this agreement took place, the project manager approached the analyst with a request to change several requirements.
What course of action SHOULD. the business analyst take?
A few days after this agreement took place, the project manager approached the analyst with a request to change several requirements.
What course of action SHOULD. the business analyst take?
Correct Answer: A
Question 7
The following requirements have been elicited during an interview with the warehousing manager:
REQ#1 - The system shall allow inventory levels to be modified to reflect stock wastage.
REQ#2 - The system will automatically reorder stock that has fallen below the minimum reorder level.
What kind of requirements are these?
REQ#1 - The system shall allow inventory levels to be modified to reflect stock wastage.
REQ#2 - The system will automatically reorder stock that has fallen below the minimum reorder level.
What kind of requirements are these?
Correct Answer: A
Question 8
A developer working to implement a set of baselined requirements has called the business analyst responsible for the project to check her understanding of a key requirement. During the conversation, it becomes clear to both parties that the developer is working on an older version of the requirement.
Which element of requirements management has failed?
Which element of requirements management has failed?
Correct Answer: A