Question 1
A client partition has disk storage provided by two different hosting partitions. What method of disk protection on the client partition will help ensure that the client partition remains running in the event one of the hosting partitions becomes unavailable?
Correct Answer: C
Question 2
On a Power 740, static IP addresses have previously been configured on the FSP for both HMC1 and HMC2 ports. These addresses are currently not known. How can the addresses be determined in order to access ASMI and connect the system to an HMC?
Correct Answer: B
Question 3
An optical drive is owned by a VIO Server and shared between multiple IBM i partitions as virtual optical devices.
An administrator wants to use the virtual optical device on an IBM i partition, but WRKHDWRSC *STG shows that the virtual IOP is "Inoperative."
After verifying that the device is correctly allocated to the partition, what action should be taken?
An administrator wants to use the virtual optical device on an IBM i partition, but WRKHDWRSC *STG shows that the virtual IOP is "Inoperative."
After verifying that the device is correctly allocated to the partition, what action should be taken?
Correct Answer: C
Question 4
A client plans to add a Power 770 server to a POWEP6 environment. What resource can the administrator use to determine if the HMC is at the correct level to support the new server firmware?
Correct Answer: A
Question 5
A client IBM i partition, with multipath SAN disk provided by dual VIO Servers, has used most of its available storage. Extra disk storage is required.
Several spare LUN5 (hdisks) are already mapped to the VIO Servers.
The administrator runs identical commands on the VIO Servers to create the bridging devices to define the two new LUNs to the client partition.
SST on the IBM i partition shows 4 new1 unconfigured disks.
Which statement explains why4 disks appeared, instead of 2?
Several spare LUN5 (hdisks) are already mapped to the VIO Servers.
The administrator runs identical commands on the VIO Servers to create the bridging devices to define the two new LUNs to the client partition.
SST on the IBM i partition shows 4 new1 unconfigured disks.
Which statement explains why4 disks appeared, instead of 2?
Correct Answer: D
Question 6
One partition on a multi-LPAR Power 720 has recently posted an error message about the upcoming expiration of a cache battery.
How can all the other controllers on the partitions be checked to determine if they should have the same type of maintenance performed?
How can all the other controllers on the partitions be checked to determine if they should have the same type of maintenance performed?
Correct Answer: C
Question 7
A customer needs to replace a failed tape controller card on a running partition. The service action Serviceability-> Hardware -> Exchange ERU has been started. The card has been selected and the service action has been launched.
The message "The requested service action cannot currently be completed from this management console" is displayed.
What is the most likely reason for this error?
The message "The requested service action cannot currently be completed from this management console" is displayed.
What is the most likely reason for this error?
Correct Answer: D
Question 8
A customer with an IBM i environment running on a 6-core Power 720 wants to add an additional IBM i workload in a new partition. The customer is licensed for4 cores to run IBM i, and the existing LPARs are using 3.
Maximum internal DASD is currently installed in the CEO and is being used for production. The customer has a V7000 storage subsystem with available capacity and an available slot for a fibre adapter.
Which option would allow the customer to use some of the remaining processing capabilities of their Power 720 but attach to disk storage elsewhere?
Maximum internal DASD is currently installed in the CEO and is being used for production. The customer has a V7000 storage subsystem with available capacity and an available slot for a fibre adapter.
Which option would allow the customer to use some of the remaining processing capabilities of their Power 720 but attach to disk storage elsewhere?
Correct Answer: B